Merck & Co. West Point, PA
Description
Upgraded 3,600 sf of existing spaces in collaboration with IPS, the construction manager, to create new production areas, process rooms, and support spaces. The project included steel structural framing to support active pharmaceutical production. The scope featured the installation of uPVC Pharmawall walls and ceilings, Whiterock overlay on existing walls, and a Laminar Flow Modular Ceiling to meet cleanroom standards
Industry
Pharmaceutical
Project Delivery
Design Assist
ISO Class
ISO 5, 7
Similar Projects
Doctor’s Community Hospital
Doctor’s Community Hospital engaged Hodess to deliver an ISO 7 and ISO 8 cleanroom pharmacy in Lanham, Maryland, under a design-build model. The project…
View Project